Scheme Details
DISTRICT
Farrukhabad
AGENCY
GVPR
SCHEME ID
20038537
SCHEME NAME
SIYAPUR Multi W/S Scheme
ESTIMATED COST
402.71
EXPENDITURE
203.21
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14918.00
Meter
Length Laid
14103.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Kamalganj | Siyan Pur | 418720 | Siyan Pur | 284 | 262 | 92% | Work In Progress | Not Certified |
| 2 | Farrukhabad | Kamalganj | Fatehullah Pur | 418721 | Fatehullah Pur | 260 | 228 | 88% | Work In Progress | Not Certified |
| 3 | Farrukhabad | Kamalganj | Fatehpur Raysaheb | 418722 | Fatehpur Raysaheb | 157 | 139 | 89% | Work In Progress | Not Certified |