Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20038559
SCHEME NAME Ralbhari Water Supply Scheme
ESTIMATED COST 354.07
EXPENDITURE 224.38
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12535.00 Meter
Length Laid 12535.00 Meter

Scheme Assigned Villages

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Fatehpur Ralbhari 434675 Kodri 20 20 100% Har Ghar Jal Certified
2 Barabanki Fatehpur Ralbhari 434693 Ralbhari 334 334 100% Har Ghar Jal Certified
3 Barabanki Fatehpur Ralbhari 434694 Bibipur 33 33 100% Har Ghar Jal Certified
4 Barabanki Fatehpur Ralbhari 434695 Bhundwa 91 91 100% Har Ghar Jal Certified
5 Barabanki Fatehpur Ralbhari 434696 Bhundia 35 35 100% Har Ghar Jal Certified