Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bijnor
AGENCY Vindhya-GAJA (JV)
SCHEME ID 20038586
SCHEME NAME Pauta & Pauti Gram Panchayat Water Supply
ESTIMATED COST 535.05
EXPENDITURE 277.70
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 7
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 44
Procured 45 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15753.00 Meter
Length Laid 6230.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

6 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bijnor Noorpur Pauti 387547 Pauti 281 281 100% Har Ghar Jal Not Certified
2 Bijnor Noorpur Pauta 387565 Pauta 227 226 100% Work In Progress Not Certified
3 Bijnor Noorpur Pauta 387566 Kasampur Mangal Khera 37 17 46% Work In Progress Not Certified
4 Bijnor Noorpur Pauta 387567 Jamalpur Man 165 142 86% Work In Progress Not Certified
5 Bijnor Noorpur Pauta 387568 Pandia 102 102 100% Har Ghar Jal Not Certified
6 Bijnor Noorpur Pauti 696270 ALAUDDINPUR 48 34 71% Work In Progress Not Certified