Scheme Details
DISTRICT
Sambhal
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20038827
SCHEME NAME
SIKRAURA KHADAR & BANDRAI MV WSS
ESTIMATED COST
367.68
EXPENDITURE
238.16
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12844.00
Meter
Length Laid
12776.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Junawai | Bandrai | 401024 | Bandrai | 354 | 354 | 100% | Har Ghar Jal | Not Certified |
| 2 | Sambhal | Junawai | Sikraura Khadar | 401029 | Sikraura Khadar | 353 | 353 | 100% | Har Ghar Jal | Certified |
| 3 | Sambhal | Junawai | VILASPUR | 401030 | VILASPUR | 228 | 228 | 100% | Har Ghar Jal | Not Certified |