Scheme Details
DISTRICT
Sambhal
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20038850
SCHEME NAME
CHABUTARA MV WSS
ESTIMATED COST
261.21
EXPENDITURE
69.76
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8075.00
Meter
Length Laid
7899.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Junawai | Chabutara | 401070 | Chabutara | 507 | 485 | 96% | Work In Progress | Not Certified |
| 2 | Sambhal | Junawai | KHERAFATTEHPUR | 401071 | KHERA FATAHPUR | 197 | 172 | 87% | Work In Progress | Not Certified |
| 3 | Sambhal | Junawai | KHERAFATTEHPUR | 401072 | ALLIPUR | 76 | 1 | 1% | Work In Progress | Not Certified |
| 4 | Sambhal | Junawai | Chabutara | 401073 | Khera Chinti Khalsa | 196 | 46 | 23% | Work In Progress | Not Certified |