Scheme Details
DISTRICT
Farrukhabad
AGENCY
GVPR
SCHEME ID
20038925
SCHEME NAME
Kuberpur Dugarasi Multi V w/s scheme
ESTIMATED COST
330.98
EXPENDITURE
140.69
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
25
Procured
25
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12265.00
Meter
Length Laid
12334.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Mohammadabad | Ganpatpur Budhanpur | 418609 | Ganpatpur Budhanpur | 240 | 231 | 96% | Work In Progress | Not Certified |
| 2 | Farrukhabad | Mohammadabad | Kuberpur Dugarsi | 418613 | Kuberpur Dugarsi | 479 | 474 | 99% | Work In Progress | Not Certified |
| 3 | Farrukhabad | Mohammadabad | Kuberpur Dugarsi | 656077 | Sinaura Iswari | 40 | 38 | 95% | Work In Progress | Not Certified |