Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20040601
SCHEME NAME
Madhupur Water Supply Scheme
ESTIMATED COST
240.66
EXPENDITURE
98.17
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10191.00
Meter
Length Laid
10191.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Dewa | Madhaopur | 435097 | Madhaopur | 108 | 107 | 99% | Work In Progress | Not Certified |
| 2 | Barabanki | Dewa | Madhaopur | 435098 | Chachenda | 84 | 83 | 99% | Work In Progress | Not Certified |
| 3 | Barabanki | Dewa | Madhaopur | 435099 | Pavaiya Veeran | 100 | 99 | 99% | Work In Progress | Not Certified |