Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20040616
SCHEME NAME
Tesua Salemchak & Barcasauli Water Supply Scheme
ESTIMATED COST
235.77
EXPENDITURE
160.02
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8698.00
Meter
Length Laid
8550.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Harakh | Tesua Salemchak | 435348 | Tesua Salem Chak | 228 | 222 | 97% | Work In Progress | Not Certified |
| 2 | Barabanki | Harakh | Barbasauli | 435349 | Barvasauli | 182 | 179 | 98% | Work In Progress | Not Certified |