Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Ambedkar Nagar
AGENCY Vindhya-GAJA (JV)
SCHEME ID 20041734
SCHEME NAME TAKIYA KANOONGO WSS
ESTIMATED COST 196.91
EXPENDITURE 135.14
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 6310.00 Meter
Length Laid 3345.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Ambedkar Nagar Bhiti Takiya Kanoongo 438674 Takiya Kanoongo 150 149 99% Work In Progress Not Certified
2 Ambedkar Nagar Bhiti Takiya Kanoongo 438675 Takiya Kaloo 78 70 90% Work In Progress Not Certified
3 Ambedkar Nagar Bhiti Takiya Kanoongo 438676 Yadavpur 45 45 100% Har Ghar Jal Not Certified