Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20042166
SCHEME NAME
chendri akbarpur village water supply scheme
ESTIMATED COST
272.20
EXPENDITURE
122.41
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9140.00
Meter
Length Laid
9256.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Chhajlet | Chendri Akbarpur | 387953 | Chendri Akbarpur | 248 | 241 | 97% | Work In Progress | Not Certified |
| 2 | Moradabad | Chhajlet | Chendri Akbarpur | 387954 | Chak Hafeezpur | 12 | 7 | 58% | Work In Progress | Not Certified |
| 3 | Moradabad | Chhajlet | Chendri Akbarpur | 387955 | Malliwala | 175 | 167 | 95% | Work In Progress | Not Certified |