Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20042177
SCHEME NAME
Ahemadpur nigo nagala village water supply scheme
ESTIMATED COST
233.54
EXPENDITURE
104.17
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11237.00
Meter
Length Laid
11237.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Chhajlet | Ahemadpur Nigo Nagala | 388020 | Sabdalpur Boriwala | 1 | 1 | 100% | Har Ghar Jal | Not Certified |
| 2 | Moradabad | Chhajlet | Ahemadpur Nigo Nagala | 388021 | Barodi Beeran | 3 | 2 | 67% | Work In Progress | Not Certified |
| 3 | Moradabad | Chhajlet | Ahemadpur Nigo Nagala | 388022 | Rasoolpur Gujar Dhyansingh | 191 | 186 | 97% | Work In Progress | Not Certified |
| 4 | Moradabad | Chhajlet | Ahemadpur Nigo Nagala | 388023 | Ahemadpur Nigo Nagala | 208 | 204 | 98% | Work In Progress | Not Certified |
| 5 | Moradabad | Chhajlet | Ahemadpur Nigo Nagala | 388024 | Barudi Phatehullapur | 3 | 2 | 67% | Work In Progress | Not Certified |