Scheme Details
DISTRICT
Ambedkar Nagar
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20042519
SCHEME NAME
MASODA WSS
ESTIMATED COST
453.17
EXPENDITURE
277.24
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
35199.00
Meter
Length Laid
31988.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Bhiyaon | Mirzapur | 438408 | Mirzapur | 130 | 127 | 98% | Work In Progress | Not Certified |
| 2 | Ambedkar Nagar | Bhiyaon | Mirzapur | 438409 | Natthupur Khurd | 73 | 66 | 90% | Work In Progress | Not Certified |
| 3 | Ambedkar Nagar | Bhiyaon | Mirzapur | 438410 | Dulhupur Khurd | 21 | 21 | 100% | Har Ghar Jal | Not Certified |
| 4 | Ambedkar Nagar | Bhiyaon | Mirzapur | 438411 | Khalishpur Godam | 103 | 102 | 99% | Work In Progress | Not Certified |
| 5 | Ambedkar Nagar | Bhiyaon | Mirzapur | 438412 | Manhgipur | 16 | 10 | 62% | Work In Progress | Not Certified |
| 6 | Ambedkar Nagar | Bhiyaon | MASODA | 438413 | MASODA | 330 | 305 | 92% | Work In Progress | Not Certified |