Scheme Details
DISTRICT
Ayodhya
AGENCY
VSA
SCHEME ID
20043861
SCHEME NAME
DILIGIRDHAR & UPADHYA PUR WSS
ESTIMATED COST
305.42
EXPENDITURE
261.84
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13698.00
Meter
Length Laid
9150.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Milkipur | DILIGIRDHAR | 436652 | DILIGIRDHAR | 241 | 241 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ayodhya | Milkipur | UDHUI | 436654 | SARAY HEMRAJ | 164 | 164 | 100% | Har Ghar Jal | Not Certified |
| 3 | Ayodhya | Milkipur | UPADHYAYPUR | 436656 | UPADHYAPUR | 186 | 186 | 100% | Har Ghar Jal | Not Certified |