Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20044212
SCHEME NAME BARAUD VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST 216.53
EXPENDITURE 140.26
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11313.00 Meter
Length Laid 7500.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Suithkala Baraud 468241 Baraud 126 126 100% Har Ghar Jal Not Certified
2 Jaunpur Suithkala Baraud 468242 Asharafpur 54 54 100% Har Ghar Jal Not Certified
3 Jaunpur Suithkala Baraud 468243 Mustafabad 46 46 100% Har Ghar Jal Not Certified
4 Jaunpur Suithkala Baraud 468244 Chakmariyam 2 2 100% Har Ghar Jal Not Certified