Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20045618
SCHEME NAME
CHAUDHARPUR & SHAHALAMPUR VILLAGE WATER SUPPLY SCHEME.
ESTIMATED COST
332.57
EXPENDITURE
229.80
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8042.00
Meter
Length Laid
7800.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Moradabad | Chaudharpur | 388207 | Chaudharpur | 718 | 709 | 99% | Work In Progress | Not Certified |
| 2 | Moradabad | Moradabad | SHAHALAMPUR | 388208 | SHAHALAMPUR | 223 | 219 | 98% | Work In Progress | Not Certified |