Scheme Details
DISTRICT
Bijnor
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20048030
SCHEME NAME
Gopalpur & Lalpur Water Supply Scheme
ESTIMATED COST
454.74
EXPENDITURE
416.18
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18533.00
Meter
Length Laid
17986.00
Meter
Scheme Assigned Villages
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kiratpur | Lalpur | 385863 | Lalpur | 106 | 106 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bijnor | Kiratpur | Lalpur | 385864 | Jewanpur | 70 | 70 | 100% | Har Ghar Jal | Not Certified |
| 3 | Bijnor | Kiratpur | Lalpur | 385865 | Haqiqatpur Prayag | 43 | 43 | 100% | Har Ghar Jal | Not Certified |
| 4 | Bijnor | Kiratpur | Lalpur | 385866 | Haridaspur Madhe | 23 | 23 | 100% | Har Ghar Jal | Not Certified |
| 5 | Bijnor | Kiratpur | Gopalpur | 385931 | Gopalpur | 127 | 127 | 100% | Har Ghar Jal | Not Certified |
| 6 | Bijnor | Kiratpur | Gopalpur | 385932 | Aurangjebpur Fazil | 68 | 68 | 100% | Har Ghar Jal | Not Certified |
| 7 | Bijnor | Kiratpur | Gopalpur | 385933 | Haqiqatpur Virchand | 113 | 113 | 100% | Har Ghar Jal | Not Certified |