| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | GA INFRA - BABA (JV) | 20049623 | BHAWARAIPUR PATTI BANKARAI WATER SUPPLY SCHEME | 199.63 | 125.30 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | NA | 0 | NA | No | 8257.00 | 1003.00 |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 0 | NA | 0 | NA | No | 7358.00 | 6500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Bilariaganj | Bhawaraipur Patti Bankarai | 462096 | Patti Tandan Rai | 180 | 180 | 100 | Har Gar Jal | Not Certified |
| 2 | Azamgarh | Bilariaganj | Bhawaraipur Patti Bankarai | 462097 | Phulwariya | 106 | 106 | 100 | Har Gar Jal | Certified |
| 3 | Azamgarh | Bilariaganj | Bhawaraipur Patti Bankarai | 462098 | Gayaspur | 45 | 45 | 100 | Har Gar Jal | Certified |