Scheme Details
DISTRICT Kanpur Dehat
AGENCY VSA
SCHEME ID 20050118
SCHEME NAME Mirgaon
ESTIMATED COST 205.32
EXPENDITURE 129.28
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 6414.00 Meter
Length Laid 6100.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Kanpur Dehat Rajpur Mirgaon 421871 Mirgaon 416 413 99% Work In Progress Not Certified