Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Rithwik-Koya (JV) | 20050271 | Budhanpur Buzurg JJM | 317.96 | 42.28 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 23 | 23 | Yes | 0 | NA | No | 18690.00 | 0.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Budhnapar Bujurg | 455881 | Budhnapar Bujurg | 140 | 3 | 2 | Work In Progress | Not Certified | 
| 2 | Gorakhpur | Uruwa | Budhnapar Bujurg | 455882 | Bankati Khurd | 60 | 60 | 100 | Har Gar Jal | Not Certified | 
| 3 | Gorakhpur | Uruwa | Budhnapar Bujurg | 455883 | Bankati Bujurg | 119 | 49 | 41 | Work In Progress | Not Certified | 
| 4 | Gorakhpur | Uruwa | Budhnapar Bujurg | 455884 | Yadupatti | 118 | 118 | 100 | Har Gar Jal | Not Certified | 
| 5 | Gorakhpur | Uruwa | Budhnapar Bujurg | 455885 | Budhapar Khurd | 7 | 7 | 100 | Har Gar Jal | Not Certified |