Scheme Details
DISTRICT
Sambhal
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20050335
SCHEME NAME
ABU NAGAR MV WSS
ESTIMATED COST
188.99
EXPENDITURE
87.41
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7905.00
Meter
Length Laid
7600.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sambhal | Sambhal | Abu Nagar | 389146 | Abu Nagar | 183 | 183 | 100% | Har Ghar Jal | Not Certified |
| 2 | Sambhal | Sambhal | Abu Nagar | 389147 | Handalpur | 180 | 119 | 66% | Work In Progress | Not Certified |