Scheme Details
DISTRICT
Gorakhpur
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20050346
SCHEME NAME
Bedauli JJM
ESTIMATED COST
332.28
EXPENDITURE
114.70
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
19230.00
Meter
Length Laid
19230.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Barhalganj | Bedauli | 457316 | Bedauli | 443 | 439 | 99% | Work In Progress | Not Certified |
| 2 | Gorakhpur | Barhalganj | Bedauli | 457317 | Babhnauli | 58 | 58 | 100% | Har Ghar Jal | Not Certified |
| 3 | Gorakhpur | Barhalganj | Bedauli | 457318 | Sarbasi | 10 | 7 | 70% | Work In Progress | Not Certified |