Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20050430
SCHEME NAME AGAHUWA & SARAI DEWA WATER SUPPLY SCHEME
ESTIMATED COST 416.23
EXPENDITURE 274.99
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 26283.00 Meter
Length Laid 17144.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Machhlishahr Sarai Dewa 469647 Sarai Dewa 173 168 97% Work In Progress Not Certified
2 Jaunpur Machhlishahr Sarai Dewa 469648 Dewapur 42 37 88% Work In Progress Not Certified
3 Jaunpur Machhlishahr Agahuwa 469654 Agahuwa 208 206 99% Work In Progress Not Certified
4 Jaunpur Machhlishahr Agahuwa 469655 Sawaiya 134 132 99% Work In Progress Not Certified