Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20050457 | GAJDHARPUR & PURA BALAI WATER SUPPLY SCHEME | 387.93 | 159.14 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 31843.00 | 29457.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Mahrajganj | Pura Balai | 468895 | Col | 105 | 100 | 95 | Work In Progress | Not Certified |
| 2 | Jaunpur | Mahrajganj | Pura Balai | 468896 | Pura Balai | 149 | 138 | 93 | Work In Progress | Not Certified |
| 3 | Jaunpur | Mahrajganj | Gajadharpur | 468898 | Abhaipur | 13 | 11 | 85 | Work In Progress | Not Certified |
| 4 | Jaunpur | Mahrajganj | Gajadharpur | 468899 | Gajhar Mau | 91 | 83 | 91 | Work In Progress | Not Certified |
| 5 | Jaunpur | Mahrajganj | Gajadharpur | 468900 | Gajadharpur | 106 | 98 | 92 | Work In Progress | Not Certified |