Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20050491
SCHEME NAME BARPUR WATER SUPPLY SCHEME
ESTIMATED COST 269.09
EXPENDITURE 49.46
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 0
Air Compressor Done 0
O.P. Unit Done 0
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 16
Procured 0 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 18305.00 Meter
Length Laid 0.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Sujanganj Bar Pur 469301 Barpur 183 2 1% Work In Progress Not Certified
2 Jaunpur Sujanganj Bar Pur 469302 Purabeni 62 2 3% Work In Progress Not Certified
3 Jaunpur Sujanganj Bar Pur 469303 Alampur 36 2 6% Work In Progress Not Certified