Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20050495 | MIRAPUR KALAWAL WATER SUPPLY SCHEME | 282.03 | 47.23 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 0 | 0 | 0 | 1 | 1 | 0 | 16 | 0 | NA | 0 | NA | No | 18321.00 | 8958.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Mahrajganj | Mirapur Kalawal | 468892 | Mirapur Kalawal | 126 | 91 | 72 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Mahrajganj | Mirapur Kalawal | 468893 | Markha Pur | 108 | 67 | 62 | Work In Progress | Not Certified | 
| 3 | Jaunpur | Mahrajganj | Mirapur Kalawal | 468894 | Kurethuwa | 32 | 12 | 38 | Work In Progress | Not Certified |