Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20050663
SCHEME NAME CHHANGAPUR NO 2 WATER SUPPLY SCHEME
ESTIMATED COST 435.37
EXPENDITURE 139.01
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 29742.00 Meter
Length Laid 8425.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Ramnagar Chhangapur No. 2 470799 Banpurva 96 47 49% Work In Progress Not Certified
2 Jaunpur Ramnagar Chhangapur No. 2 470800 Chhangapur 296 215 73% Work In Progress Not Certified
3 Jaunpur Ramnagar Chhangapur No. 2 470801 Manapur 42 12 29% Work In Progress Not Certified
4 Jaunpur Ramnagar Chhangapur No. 2 470802 Dinapur 84 42 50% Work In Progress Not Certified