Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | LC INFRA | 20050675 | RASANDA GP RWSS | 243.01 | 137.79 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 10510.00 | 9820.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tarwan | Rasanda | 464542 | Prasotam Pur | 81 | 76 | 94 | Work In Progress | Not Certified |
| 2 | Azamgarh | Tarwan | Rasanda | 464543 | Rasanda | 138 | 130 | 94 | Work In Progress | Not Certified |
| 3 | Azamgarh | Tarwan | Rasanda | 464544 | Gopal Pur | 25 | 20 | 80 | Work In Progress | Not Certified |
| 4 | Azamgarh | Tarwan | Rasanda | 464545 | Asmal Pur | 61 | 56 | 92 | Work In Progress | Not Certified |
| 5 | Azamgarh | Tarwan | Rasanda | 464546 | Araji Meru Pur | 68 | 63 | 93 | Work In Progress | Not Certified |