Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Jaunpur
AGENCY AFCONS
SCHEME ID 20050700
SCHEME NAME NADIYANVA WATER SUPPLY SCHEME
ESTIMATED COST 286.31
EXPENDITURE 130.26
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19368.00 Meter
Length Laid 13364.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Jaunpur Mariyahun Nadiyanva 469771 Nadiyanva 205 192 94% Work In Progress Not Certified
2 Jaunpur Mariyahun Nadiyanva 469772 Patti 57 26 46% Work In Progress Not Certified
3 Jaunpur Mariyahun Nadiyanva 469773 Bhubhuwar 75 65 87% Work In Progress Not Certified