Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Sambhal
AGENCY SPML Infra
SCHEME ID 20050825
SCHEME NAME RAWAN KHURD URF BIBIPUR
ESTIMATED COST 162.37
EXPENDITURE 65.67
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 25
Transformer Procured NA
Work Status No
Distribution Line
Total Length 5396.00 Meter
Length Laid 5396.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sambhal Sambhal RAYKHURD URF BIBIPUR 389063 RAWAN KHURD URF BIBIPUR 445 349 78% Work In Progress Not Certified