Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20051009
SCHEME NAME
HUSAINPUR HAMIR VILLAGE WATER SUPPLY SCHEME
ESTIMATED COST
424.38
EXPENDITURE
136.49
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
15806.00
Meter
Length Laid
15500.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Dingarpur | Husainpur Hamir | 388392 | Husainpur Hamir | 518 | 517 | 100% | Work In Progress | Not Certified |
| 2 | Moradabad | Dingarpur | Chirawli | 388393 | Chirawli | 400 | 399 | 100% | Work In Progress | Not Certified |