Scheme Details
DISTRICT Moradabad
AGENCY NKG-PRIMUS (JV)
SCHEME ID 20051018
SCHEME NAME Peepli ahir M S T village water supply scheme
ESTIMATED COST 320.77
EXPENDITURE 127.03
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11616.00 Meter
Length Laid 11000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Moradabad Thakurdwara Peepli Ahir (m.s.t.) 387695 Peepli Ahir (m.s.t.) 418 410 98% Work In Progress Not Certified
2 Moradabad Thakurdwara Peepli Ahir (m.s.t.) 387696 Peepli Ghanshyam (m.s.t) 89 81 91% Work In Progress Not Certified