Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | VISHVARAJ | 20051077 | BHADERA +1 MULTI GP WATER SUPPLY SCHEME | 323.55 | 235.48 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 22 | 22 | Yes | 0 | NA | No | 10213.00 | 10127.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pilibhit | Bisalpur | Adhilabad Bisalpur | 405229 | Karanpur Layakram | 69 | 51 | 74 | Work In Progress | Not Certified |
| 2 | Pilibhit | Bisalpur | Adhilabad Bisalpur | 405230 | Aadilabad Bisalpur | 128 | 108 | 84 | Work In Progress | Not Certified |
| 3 | Pilibhit | Bisalpur | Bhadera | 405280 | Bhadera | 256 | 253 | 99 | Work In Progress | Not Certified |
| 4 | Pilibhit | Bisalpur | Bhadera | 405281 | Bhadhari | 111 | 108 | 97 | Work In Progress | Not Certified |