Scheme Details
DISTRICT
Ayodhya
AGENCY
VSA
SCHEME ID
20051325
SCHEME NAME
SARAI MANODHAR AND KAUN DADA
ESTIMATED COST
480.07
EXPENDITURE
356.30
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
30581.00
Meter
Length Laid
30581.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Tarun | Saray Manodher | 437426 | Saray Manodher | 420 | 420 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ayodhya | Tarun | Saray Manodher | 437427 | Udai Pur | 67 | 67 | 100% | Har Ghar Jal | Not Certified |
| 3 | Ayodhya | Tarun | Kuaan Dand | 437428 | Kuaan Dand | 224 | 224 | 100% | Har Ghar Jal | Not Certified |