Scheme Details
DISTRICT
Lakhimpur Kheri
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20052115
SCHEME NAME
CHANDARASA KHURD JJM SCHEME
ESTIMATED COST
218.60
EXPENDITURE
184.63
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8405.00
Meter
Length Laid
8375.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Isanagar | Chandrasa Khurd | 409442 | Chandrasa Khurd | 408 | 403 | 99% | Work In Progress | Not Certified |