Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | NCC Ltd. | 20052573 | HARRIYA JJM SCHEME | 245.92 | 93.64 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 14 | Yes | 0 | NA | No | 9170.00 | 9031.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Behjam | Harriya | 408962 | Harriya | 183 | 182 | 99 | Work In Progress | Not Certified | 
| 2 | Lakhimpur Kheri | Behjam | Harriya | 408963 | Malpur Gudriya | 148 | 143 | 97 | Work In Progress | Not Certified | 
| 3 | Lakhimpur Kheri | Behjam | Harriya | 408964 | Korie | 126 | 109 | 87 | Work In Progress | Not Certified |