| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | NCC Ltd. | 20052578 | BHAGWATIPUR JJM SCHEME | 224.62 | 116.73 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 14 | Yes | 0 | NA | No | 5614.00 | 4728.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Mitoli | Bhagwatipur | 408638 | Bhagwatipur | 361 | 361 | 100 | Har Gar Jal | Not Certified |
| 2 | Lakhimpur Kheri | Mitoli | Bhagwatipur | 408639 | Bisarikheda | 110 | 110 | 100 | Har Gar Jal | Not Certified |