Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Pratapgarh
AGENCY Power Mech Projects Ltd
SCHEME ID 20052950
SCHEME NAME Saphachhat Gram Panchayat Water Supply Scheme
ESTIMATED COST 332.05
EXPENDITURE 212.05
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 23464.00 Meter
Length Laid 23464.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pratapgarh Aaspur Devsara Sapaha Chhat 430521 Sapaha Chhat 307 307 100% Har Ghar Jal Not Certified
2 Pratapgarh Aaspur Devsara Sapaha Chhat 430522 Upadhayaipur 45 45 100% Har Ghar Jal Not Certified
3 Pratapgarh Aaspur Devsara Sapaha Chhat 430523 Arjunpur 117 82 70% Work In Progress Not Certified