Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Bareilly NCC Ltd. 20053231 Bankauli 306.73 158.12 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 1 1 1 1 1 1 0 21 21 Yes 0 NA No 9887.00 9289.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Bareilly Baheri Bankauli 402718 Bankauli 400 400 100 Har Gar Jal Not Certified
2 Bareilly Baheri Bankauli 402719 Nawayal 100 100 100 Har Gar Jal Not Certified
3 Bareilly Baheri Bankauli 402720 Bahudanpur 44 44 100 Har Gar Jal Not Certified