Scheme Details
DISTRICT Pilibhit
AGENCY VISHVARAJ
SCHEME ID 20053310
SCHEME NAME BHIMPUR NAUGALA GP WATER SUPPLY SCHEME
ESTIMATED COST 237.20
EXPENDITURE 149.97
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15834.00 Meter
Length Laid 15163.00 Meter

Scheme Assigned Villages

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Pilibhit Puranpur Bhimpur Naugaja 405610 Bhimpur Naugaja 108 101 94% Work In Progress Not Certified
2 Pilibhit Puranpur Bhimpur Naugaja 405611 Chitarpur 131 120 92% Work In Progress Not Certified
3 Pilibhit Puranpur Bhimpur Naugaja 405612 Keshopur T.anandpur 39 28 72% Work In Progress Not Certified
4 Pilibhit Puranpur Bhimpur Naugaja 405613 Birkhera T.madhau Tanda 65 63 97% Work In Progress Not Certified