Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Bareilly | NCC Ltd. | 20053447 | PanwariA Mustakil,Tihar Khera & Bholapur Shankhapur | 226.86 | 109.57 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 14 | Yes | 0 | NA | No | 6386.00 | 6300.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Fatehganj West | Panvaria Mustakil | 403120 | Panvaria Mustakil | 270 | 270 | 100 | Har Gar Jal | Not Certified | 
| 2 | Bareilly | Fatehganj West | Rahpura Jagir | 403191 | Tihar Khera | 61 | 61 | 100 | Har Gar Jal | Not Certified | 
| 3 | Bareilly | Kyara | Bholapur Shankhapur | 403356 | Bholapur Shankhapur | 121 | 121 | 100 | Har Gar Jal | Not Certified |