Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Bareilly NCC Ltd. 20053649 Pandera & Sisai 349.95 185.98 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 1 30 30 Yes 0 NA No 9970.00 9970.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Bareilly Baheri Pandera 402740 Pandera 392 392 100 Har Gar Jal Not Certified
2 Bareilly Baheri Sisai 402745 Sisai 238 238 100 Har Gar Jal Not Certified