Scheme Details
DISTRICT
Gorakhpur
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20053719
SCHEME NAME
BHAIRWA ABADI SAKHANI JJM
ESTIMATED COST
345.15
EXPENDITURE
195.81
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17710.00
Meter
Length Laid
17535.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Bhathat | Bhairwa | 455301 | Bhairwa | 334 | 334 | 100% | Har Ghar Jal | Not Certified |
| 2 | Gorakhpur | Bhathat | Abadi Sakhani | 455380 | Abadi Sakhani | 375 | 311 | 83% | Work In Progress | Not Certified |