Scheme Details
DISTRICT
Gorakhpur
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20053966
SCHEME NAME
LAKHANAPARJJM
ESTIMATED COST
264.13
EXPENDITURE
126.32
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12.69
Meter
Length Laid
10160.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Pali | Lakhanapar | 454901 | Lakhanapar | 340 | 340 | 100% | Har Ghar Jal | Not Certified |
| 2 | Gorakhpur | Pali | Lakhanapar | 454902 | Gulaur | 32 | 6 | 19% | Work In Progress | Not Certified |
| 3 | Gorakhpur | Pali | Lakhanapar | 454903 | Bhikhara | 63 | 20 | 32% | Work In Progress | Not Certified |
| 4 | Gorakhpur | Pali | Lakhanapar | 454904 | Nibi | 6 | 3 | 50% | Work In Progress | Not Certified |
| 5 | Gorakhpur | Pali | Lakhanapar | 454905 | Karmuwa | 3 | 1 | 33% | Work In Progress | Not Certified |