Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20054710
SCHEME NAME
Fareedpur Kasam Village Water Supply Scheme
ESTIMATED COST
244.33
EXPENDITURE
112.28
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6313.00
Meter
Length Laid
5931.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Dilari | Fareedpur Kasam | 387850 | Fareedpur Kasam | 203 | 197 | 97% | Work In Progress | Not Certified |
| 2 | Moradabad | Dilari | Fareedpur Kasam | 387851 | Jogipura | 193 | 186 | 96% | Work In Progress | Not Certified |