Scheme Details
DISTRICT
Sultanpur
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20054853
SCHEME NAME
ROHINI KHOJAGIPUR & BASNA WATER SUPPLY SCHEME
ESTIMATED COST
377.75
EXPENDITURE
154.48
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
24911.00
Meter
Length Laid
24115.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Dostpur | Basna | 441202 | Bharopur | 93 | 92 | 99% | Work In Progress | Not Certified |
| 2 | Sultanpur | Dostpur | Basna | 441203 | Basna | 110 | 108 | 98% | Work In Progress | Not Certified |
| 3 | Sultanpur | Dostpur | Rohini Khojagipur | 441204 | Rohini Khojagipur | 266 | 262 | 98% | Work In Progress | Not Certified |