Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Rampur | OMIL-JWIL (JV) | 20054870 | KALRAKH AND HARYAL AND KHAJURIYA GP W/S SCHEME | 307.01 | 162.68 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 7937.00 | 7879.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Rampur | Chamraua | Khajuriya | 389898 | Khajuriya | 262 | 262 | 100 | Har Gar Jal | Certified |
| 2 | Rampur | Chamraua | Kalrakh | 389899 | Kalrakh | 192 | 192 | 100 | Har Gar Jal | Certified |
| 3 | Rampur | Chamraua | Haryal | 389905 | Haryal | 284 | 284 | 100 | Har Gar Jal | Certified |