Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20055488
SCHEME NAME
Tanda Afzal (M.S.T) Village Water Supply Scheme
ESTIMATED COST
209.55
EXPENDITURE
105.78
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6529.00
Meter
Length Laid
6483.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Thakurdwara | Tanda Afzal(m.s.t) | 387703 | Tanda Afzal(m.s.t) | 98 | 95 | 97% | Work In Progress | Not Certified |
| 2 | Moradabad | Thakurdwara | Tanda Afzal(m.s.t) | 387704 | Preetampur | 72 | 56 | 78% | Work In Progress | Not Certified |
| 3 | Moradabad | Thakurdwara | Tanda Afzal(m.s.t) | 387705 | Man Patti (m.s.t.) | 57 | 54 | 95% | Work In Progress | Not Certified |
| 4 | Moradabad | Thakurdwara | Tanda Afzal(m.s.t) | 387706 | Man Patti(a.h.t) | 12 | 9 | 75% | Work In Progress | Not Certified |
| 5 | Moradabad | Thakurdwara | Tanda Afzal(m.s.t) | 387707 | Lamba Khera | 111 | 108 | 97% | Work In Progress | Not Certified |