Scheme Details
DISTRICT
Sultanpur
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20055650
SCHEME NAME
GYASPUR & HADAI WATER SUPPLY SCHEME
ESTIMATED COST
465.48
EXPENDITURE
208.42
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
27765.00
Meter
Length Laid
27423.00
Meter
Scheme Assigned Villages
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Dostpur | Hadai | 441236 | Pipara Bhawanipur | 124 | 117 | 94% | Work In Progress | Not Certified |
| 2 | Sultanpur | Dostpur | Hadai | 441237 | Karnaipur Raghobanshi | 52 | 47 | 90% | Work In Progress | Not Certified |
| 3 | Sultanpur | Dostpur | Gyaspur | 441249 | Gyaspur | 165 | 162 | 98% | Work In Progress | Not Certified |
| 4 | Sultanpur | Dostpur | Gyaspur | 441250 | Mahuaari Ashapur | 113 | 106 | 94% | Work In Progress | Not Certified |
| 5 | Sultanpur | Dostpur | Gyaspur | 441251 | Saray Sahawan | 69 | 64 | 93% | Work In Progress | Not Certified |
| 6 | Sultanpur | Dostpur | Hadai | 638904 | Hadai | 20 | 20 | 100% | Har Ghar Jal | Not Certified |