Scheme Details
DISTRICT
Sultanpur
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20055699
SCHEME NAME
DHARAMAPUR WATER SUPPLY SCHEME
ESTIMATED COST
264.89
EXPENDITURE
169.64
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14055.00
Meter
Length Laid
14181.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Akhand Nagar | Dharamapur | 441439 | Gopalpur | 100 | 92 | 92% | Work In Progress | Not Certified |
| 2 | Sultanpur | Akhand Nagar | Dharamapur | 441440 | Jafarpur | 102 | 95 | 93% | Work In Progress | Not Certified |
| 3 | Sultanpur | Akhand Nagar | Dharamapur | 701175 | DHARMAPUR | 130 | 126 | 97% | Work In Progress | Not Certified |