Scheme Details
DISTRICT
Sultanpur
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20055876
SCHEME NAME
BANGARKALAN WATER SUPPLY SCHEME
ESTIMATED COST
301.61
EXPENDITURE
156.41
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23060.00
Meter
Length Laid
23060.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Karaundikala | Bangarkalan | 441404 | Bangarkalan | 306 | 306 | 100% | Har Ghar Jal | Not Certified |
| 2 | Sultanpur | Karaundikala | Bangarkalan | 441405 | Surjanpur | 15 | 15 | 100% | Har Ghar Jal | Not Certified |
| 3 | Sultanpur | Karaundikala | Bangarkalan | 441406 | Marufpur | 77 | 77 | 100% | Har Ghar Jal | Not Certified |